2026-11-23 weekly review
Week covered: Monday 2026-11-16 to Sunday 2026-11-22 · Review held: Monday 2026-11-23 · In the room: Marisol Vance, Teo Arriaga, Priya Nand Unusual last week: three experiments running. Second full week after the hail. Next week's calendar: Thanksgiving. The office is closed Thursday 2026-11-26 and Friday 2026-11-27. Three working days.
Previous review: Brackenfold · 2026-11-16 weekly review
1. Last week's experiments
| ID | Hypothesis | Result | The rule said | Decision |
|---|---|---|---|---|
| KZ-001 Overnight leads called before the first inspection | Wait of overnight leads (median minutes from 8:00 am) from 250 to 45 by 2026-11-20 | 170. Ran Monday and Tuesday only | Kill above 120 | Killed |
| KZ-002 Row first, then a call within fifteen minutes | Minutes to first reply (median) from 235 to 30 by 2026-11-20 | 12. Ran as designed | Keep at 30 or less | Kept |
| KZ-003 Crew and supplier calls go to Marisol before noon | Non-lead calls answered by Teo before noon from 11 a morning to 3 by 2026-11-20 | 6. Ran as designed | Change at 4 to 7 | Changed, replaced by KZ-005 |
What each one taught:
- KZ-001. On Monday and Tuesday Priya called the overnight leads by 8:30. From Wednesday her 8:30 inspection slot was booked every day, the risk written on the card, and the room had decided that a booked inspection wins. Overnight leads went back to Teo, who reached most of them by late morning. Median over the 14 overnight leads: 170. It ran two days of five, and the reason it stopped is the lesson: the idle hour it borrowed no longer exists. Killed, not tried again. Overnight leads stay with Teo at 8:00, oldest first.
- KZ-002. 36 leads: 22 in office hours, 14 overnight or on the weekend. Teo called 20 of the 22 inside 15 minutes. Two took 24 and 40 minutes. Sorted, the 18th and 19th values are 11 and 13, so the median is 12. The steps were written down on Tuesday as the storm lead response SOP, under test. Today it becomes the standard.
- KZ-003. Teo's tally for the five mornings: 7, 6, 5, 6, 6. Dale, Rufus and the supplier's rep switched on Monday, and there is no crew or supplier call on the tally after Tuesday. What is left is homeowners asking where their job or their report stands, about 6 a morning, twice what Teo remembered. He cannot answer most of them without calling Marisol. Six is in the change range, so one thing changes.
About how we experiment. The collision between KZ-001 and KZ-002 happened as written, and because the room had decided in advance which one gives way, nobody argued on Wednesday. KZ-003's target rested on a split Teo remembered, and it was off by half. A split inside a baseline is a count too: this week's tally sheet has a column for who called.
2. What moved
node scripts/trend.mjs 40-Improvement/Examples/brackenfold-metrics.csv --weeks 8 --md
Week of 2026-11-16, compared with the week of 2026-11-09. Four-week average: 2026-10-19 to 2026-11-09 (the four weeks before this one). Source: brackenfold-metrics.csv, 12 rows. Better or worse from: brackenfold-metrics.meta.json.
| Metric | Better when | Last | vs last week | 4-week avg | Against avg | Week | vs avg |
|---|---|---|---|---|---|---|---|
| New leads | higher | 36 | -11 (-23.4%) | 31.5 | above (+14.3%) | worse | better |
| Minutes to first reply (median) | lower | 12 | -223 (-94.9%) | 104.5 | below (-88.5%) | better | better |
| Inspections done | higher | 21 | +6 (+40.0%) | 13 | above (+61.5%) | better | better |
| Reports late (past 24 hours) | lower | 9 | +3 (+50.0%) | 4 | above (+125.0%) | worse | worse |
| Jobs closed | higher | 6 | +1 (+20.0%) | 5.25 | above (+14.3%) | better | better |
| Days from job close to invoice | lower | 8 | 0 (0.0%) | 6 | above (+33.3%) | same | worse |
| Callbacks | lower | 1 | 0 (0.0%) | 1.25 | below (-20.0%) | same | better |
Flag. Largest adverse move this week: Reports late (past 24 hours) 6 to 9 (+50.0%). Adverse moves, largest first: Reports late (past 24 hours) +50.0% · New leads -23.4%. Furthest on the wrong side of its four-week average: Reports late (past 24 hours), 9 against 4 (+125.0%).
Last 8 weeks, oldest first. A dash means no value.
| Metric | 09-28 | 10-05 | 10-12 | 10-19 | 10-26 | 11-02 | 11-09 | 11-16 |
|---|---|---|---|---|---|---|---|---|
| New leads | 16 | 12 | 15 | 14 | 13 | 52 | 47 | 36 |
| Minutes to first reply (median) | 23 | 25 | 22 | 20 | 23 | 140 | 235 | 12 |
| Inspections done | 13 | 11 | 12 | 12 | 11 | 14 | 15 | 21 |
| Reports late (past 24 hours) | 3 | 3 | 3 | 2 | 3 | 5 | 6 | 9 |
| Jobs closed | 6 | 5 | 6 | 6 | 6 | 4 | 5 | 6 |
| Days from job close to invoice | 4 | - | 5 | 5 | 5 | 6 | 8 | 8 |
| Callbacks | 0 | 1 | 1 | 1 | 1 | 2 | 1 | 1 |
"Flat" means within 5% of the four-week average.
Reading:
- The flag sits on the new pile. Late reports went from 6 to 9 in the week inspections went from 15 to 21. All nine are Thursday's and Friday's inspections.
- Relieving the first call released work the same week. First reply 235 to 12, inspections up by 6. The estimator's open slots are gone.
- New leads read "worse" and are not a problem. 47 to 36 is the storm draining. The eight-week row shows 12 to 16 before it.
Days from close to invoice is at 8 for the second week, against an average of 6. Still in section 6.
3. The constraint this week
The photo report. 10 inspected roofs have no report. Nine are last Thursday's and Friday's inspections. The tenth is the Hendricks roof, inspected on 2026-11-12, eleven days ago.
Queues counted by Teo Arriaga on Monday morning. The uncalled leads took one filter on the leads sheet this time, not 40 minutes in three inboxes.
| Step | Waiting now | Last week | Oldest | Waits on |
|---|---|---|---|---|
| Lead comes in, first call | 2 | 14 | Sunday evening | Teo Arriaga |
| Drone inspection on site | 9 booked, each waiting for its day | 6 | Booked for this week | Priya Nand |
| Photo report to the homeowner | 10 | 4 | 11 days | Priya Nand |
| Estimate and insurance paperwork | 3 | 3 | 2 days | Marisol Vance |
| Job scheduled, materials ordered | 3 | 3 | 5 days | Marisol Vance |
| Walkthrough and close | 2 | 2 | 3 days | Marisol Vance |
| Invoice and payment | 5 | 5 | 9 days | June Halloran |
Evidence:
- The pile grows. 4 reports waiting last Monday, 10 today. Of 21 inspections, 12 reports went out inside 24 hours and 9 did not.
- The next step is short of work. Estimates waiting for approval stayed at 3 while inspections rose by 6. A roof without a report cannot get an estimate.
- It costs something now. Nine homeowners are past the 24 hours printed on the website. One of them called about it (C-016). Why the Hendricks report is still not out: unknown. Marisol asks Priya today.
The constraint has moved. The test in Finding the constraint: the old pile is under a week of work and shrinking, and another pile is growing. Two leads are waiting for a call, against 36 leads a week. The report pile went from 4 to 10.
4. Five whys
Problem: on Monday 2026-11-23, 10 inspected roofs had no report, and 9 of last week's 21 reports missed the 24 hours.
- Why were Thursday's and Friday's reports not out by Monday? Priya writes reports in the evening, after the day's inspections. Monday to Wednesday she kept up with four a day on three long evenings. With five inspections on Thursday and four on Friday there were no evenings left.
- Why only in the evening? Her day is on roofs. She timed five inspections and five reports last week: about 75 minutes per inspection with the drive, about 45 minutes per report. 21 × 75 minutes is 26.25 hours. 21 × 45 minutes is 15.75 hours, and all of it lands after 5 pm.
- Why does the estimator write all of it? Since last Monday the photos are in the job folder before she drives off (C-015, verified). Anyone could start. Nobody does, because the findings are not in the folder. They are on the paper form in her own shorthand, and in her head.
- Why are the findings only in her shorthand? The form has a roof sketch and a notes box. It has no fixed place for each finding. It was made to be read by the person who inspected, not by someone else.
Cause somebody can act on: the form does not carry the findings in a way another person can use, so only the estimator can build the report, and only at night. By her count about 10 of the 45 minutes need an estimator: the findings and the last look. The rest is choosing photos and filling the template.
Checked with: Priya Nand (timings, her evenings, the form) and the job folders for last week (photos present in all 21). Read bottom up: findings in shorthand, therefore nobody else can build, therefore she writes all of it, therefore 15.75 evening hours, therefore Thursday's and Friday's were not out.
Arithmetic, not a forecast: if her part drops from 45 minutes to 10, 21 reports take her 3.5 hours instead of 15.75. The other 35 minutes per report do not disappear. They move to the office: 21 × 35 minutes is 12.25 hours of Teo's week. That number is why KZ-006 is on the list.
5. Three experiments
This is a three-day week, so per-week targets would mislead. All three start today, run through the short week as a rehearsal, and are judged on the full week of Monday 2026-11-30 to Friday 2026-12-04, at the review of Monday 2026-12-07. The review of 2026-11-30 reports the three-day numbers and makes no keep, change or kill call.
KZ-004 · The office builds the report
| Field | |
|---|---|
| Hypothesis | If Priya numbers each finding on the form with one line per number, and Teo builds the report from the uploaded photos and the form for her to approve, then reports late moves from 9 to 3 by 2026-12-04 |
| Why 3 | A hand-off fails a few times in its first full week, and the last inspections before a weekend reach the office near closing time. Zero would be a wish |
| Move on the constraint | Take work off it |
| Cause it attacks | Why 4: the form does not carry the findings for anyone but the estimator |
| Smallest version | The same paper form, with numbers on the sketch and one written line per number. Priya uploads photos and both sides of the form before driving off and texts Teo the address. Teo builds the report when the text arrives. Priya approves from her phone. Ops Brain writes these steps down on Tuesday so both do it the same way every day; the SOP is under test until 2026-12-04 |
| Metric, and who counts it | reports_late. Teo logs each late report with its inspection time and upload time |
| Owner | Priya Nand. Said yes on 2026-11-23 |
| Start / End | 2026-11-23 / 2026-12-04 |
| Keep if | 3 or fewer |
| Change if | 4 to 6 |
| Kill if | 7 or more |
| Could hurt | Teo's 15-minute calls, kept today. Decided in the room: a new lead interrupts a report. Also depends on KZ-006, see its card |
| Commitment | C-022 |
KZ-005 · A status text to every open job, Monday and Thursday
Replaces KZ-003. Crew and supplier calls keep going to Marisol. One thing is added.
| Field | |
|---|---|
| Hypothesis | If Marisol texts every homeowner with a job in progress one status line by 8:00 on Monday and Thursday, then non-lead calls answered by Teo before noon moves from 6 a morning to 3 by 2026-12-04 |
| Why 3 | Last week's 6 a morning were almost all homeowners asking what happens next and when. A text that answers it first should remove about half. Some will still call |
| Move on the constraint | Use it fully. Under KZ-004 the report is built in Teo's day. Every status call he does not take is time for a lead or a report |
| Cause it attacks | Found in KZ-003's result: homeowners call because nothing tells them where their job stands |
| Smallest version | Marisol writes one line per open job from the job tracker and sends it from her own phone. No new tool. Teo's tally sheet gets a column for who called |
| Metric, and who counts it | The same temporary count as KZ-003: Teo's tally of non-lead calls before noon, averaged over the working mornings |
| Owner | Marisol Vance. Said yes on 2026-11-23 |
| Start / End | 2026-11-23 / 2026-12-04 |
| Keep if | 3 or fewer |
| Change if | Not available. This is the second version. An experiment is changed once |
| Kill if | 4 or more |
| Could hurt | Marisol's Monday and Thursday mornings. Nothing the other two count |
| Commitment | C-023 |
KZ-006 · A one-page report
| Field | |
|---|---|
| Hypothesis | If the report uses a one-page template (one overview photo per roof slope, one close-up and one line per numbered finding), then minutes to build one report moves from 45 to 25 by 2026-12-04 |
| Why 25 | In Priya's five timed reports, choosing and placing photos took most of the time. A fixed page with fixed places removes the choosing |
| Move on the constraint | Use it fully |
| Cause it attacks | Why 2: 45 minutes per report. At 21 reports that is more hours than the office has |
| Smallest version | Ops Brain cuts the current template to one page on Tuesday. Teo builds every report on it and times five this week and five next week |
| Metric, and who counts it | A temporary count: minutes to build one report, timed on five, averaged. Counted by Teo |
| Owner | Teo Arriaga. Said yes on 2026-11-23 |
| Start / End | 2026-11-23 / 2026-12-04 |
| Keep if | 25 or less |
| Change if | 26 to 35 |
| Kill if | Above 35 |
| Could hurt | It changes the same step as KZ-004. Also: the baseline of 45 was timed by Priya on the old template and the new number will be Teo's. Read it as "can the office build one in 25 minutes", not as the same hands before and after |
| Commitment | C-024 |
Gate: all three were run through Real improvement or a wish. Six yes each. Three owners, three metrics.
The collision, decided in the room: KZ-004 and KZ-006 change the same step in the same weeks. Both run, because KZ-004 does not fit in Teo's week without KZ-006: 21 reports at 45 minutes is 15.75 hours, at 25 minutes it is 8.75. KZ-004 is read on late reports and KZ-006 on timed minutes. If late reports fall, we will not know how much each one did. Accepted: both end up in the same SOP.
6. Not this week
- Overnight and weekend leads. 14 of 36 last week waited until morning. KZ-001 was killed, so nothing covers them. It needs paid early hours or a tool. The second is a question for Systems Brain.
- Days from close to invoice, 8 for the second week. Level set last week: 10 days, or tight cash.
- A cap on inspections per day. If late reports do not fall under KZ-004, booking four a day instead of five would keep the 24-hour promise at the price of a longer wait for an inspection. Not now: test the hand-off first.
- Who backs Teo up. The storm lead SOP names Priya as his backup. From this week her hours are the scarce ones. A question for the SOP's review on 2026-12-15.
7. Filed
| Note | What was written |
|---|---|
| Experiments | KZ-001 killed, KZ-002 kept, KZ-003 changed. Three new rows, KZ-004 to KZ-006, open. See Brackenfold · Experiments |
| Commitments | Four rows closed, four rows added, below |
| Decisions log | Two rows, below |
| For Ops Brain | Write down how the inspection report gets out within 24 hours: Priya numbers the findings and uploads, Teo builds, Priya approves. Source: experiment KZ-004 in the weekly review of 2026-11-23. Under test until 2026-12-04. and Cut the report template to one page. |
| For Systems Brain | Nothing yet. Overnight leads are parked in section 6 |
Rows closed in the ledger. C-015 was already verified by Marisol on Friday.
| ID | Commitment | Owner | Due | Status | Verified by |
|---|---|---|---|---|---|
| C-011 | Call the 14 leads that have had no first call, oldest first | Teo Arriaga | 2026-11-16 | verified | Marisol Vance, 2026-11-23: all 14 rows have a first call dated 2026-11-16 |
| C-012 | Call the overnight leads from 8:00 to 9:00 for one week | Priya Nand | 2026-11-20 | dropped | Dropped 2026-11-23: KZ-001 killed. It ran Monday and Tuesday |
| C-013 | Take crew and supplier calls on the cell from 8:00 to 12:00 for one week | Marisol Vance | 2026-11-20 | verified | Teo Arriaga, 2026-11-23: no crew or supplier call on the tally after Tuesday |
| C-014 | Reply to every storm lead within 15 minutes during office hours, for one week | Teo Arriaga | 2026-11-20 | verified | Marisol Vance, 2026-11-23: 20 of 22 inside 15 minutes, per the leads sheet |
Rows added:
| ID | Commitment | Owner | Due | Status | Source | Verified by |
|---|---|---|---|---|---|---|
| C-022 | KZ-004: number the findings on every form and approve each report Teo builds | Priya Nand | 2026-12-04 | open | Weekly review 2026-11-23 | |
| C-023 | KZ-005: text every homeowner with an open job one status line, Monday and Thursday by 8:00 | Marisol Vance | 2026-12-04 | open | Weekly review 2026-11-23 | |
| C-024 | KZ-006: build every report on the one-page template and time five a week | Teo Arriaga | 2026-12-04 | open | Weekly review 2026-11-23 | |
| C-025 | Ask Ops Brain to write down the report steps, under test, and to cut the template to one page | Marisol Vance | 2026-11-24 | open | Weekly review 2026-11-23 |
The hold check for KZ-002 needs no new row: it is the review of the storm lead response SOP, C-021, due 2026-12-15.
Rows for the decisions log:
| Date | Decision | Why | Rejected | Decided by | Check on |
|---|---|---|---|---|---|
| 2026-11-23 | Keep KZ-002: every lead gets a row on arrival and a call within 15 minutes during office hours. The storm lead response SOP is no longer under test | Median first reply went from 235 to 12 against a target of 30. 20 of 22 office-hours leads were called inside 15 minutes. Inspections went from 15 to 21 the same week | Covering evenings and weekends now: 14 of 36 leads still wait until morning, and it needs paid hours or a tool | Marisol Vance | 2026-12-15 |
| 2026-11-23 | Kill KZ-001: the estimator does not call overnight leads | Median wait 170 minutes against a kill line of 120. It ran two days; from Wednesday the hour was a booked inspection | Trying it again, or moving her first inspection to 9:30. Her hours are now the scarce ones | Marisol Vance | 2026-12-21 |
8. The owner must confirm
- Who presses send on the report. The card says Teo builds and Priya approves. It leaves open whether Priya sends it herself or Teo sends once she approves. Marisol decides when the steps are written down.
- The status text for KZ-005. Draft: "Brackenfold Roofing, Marisol here. Your roof at :
on . I will text again Thursday." It is hers to send. - Teo's week. 21 reports at 25 minutes is 8.75 hours, on top of the calls. The room decided a lead interrupts a report. If the median first reply goes above 30 while this runs, it is the first thing on the table at the next review.
- The Hendricks report. Promised on 2026-11-18 for 2026-11-19 (C-016). The reason it is not out is not written anywhere.
- The closed days. This review assumes Thursday 2026-11-26 and Friday 2026-11-27.