Automation backlog
Scored on 2026-11-18 from Brackenfold · Data map. Score = times per week × minutes each × error cost ÷ build effort. The score ranks the candidates against each other. It is not a forecast of time or money saved.
Where the numbers come from
| Number | Source |
|---|---|
| Times per week | Rows in the export ÷ the weeks they cover, shown on each line. For leads, the 33 rows of the tab plus the 14 leads Teo found with no row on 2026-11-16 |
| Minutes each | Estimates given by Priya, Teo, Marisol and June on 2026-11-18. Nobody had timed these tasks |
| Error cost | 1 = minutes to fix · 2 = a redo, a second trip or a day of delay · 3 = a lost customer, lost money or a broken promise |
| Build effort | 1 = half a day, no new tool · 2 = two or three days · 3 = one to two weeks · 5 = more than two weeks or a tool replaced |
Prerequisites: fixes that are not automations
No score. They come first because the items below cannot be built without them. Each is half a day or less in the sheets Brackenfold already has.
| # | Fix | Why it is needed (from the data map) | Blocks |
|---|---|---|---|
| P1 | One leads tab, with a Lead ID column filled when the row is created |
No key in the leads sheet. One person is in it twice. One tab per week hides everything older | 1, 2 |
| P2 | Fixed list for leads Status. One date-and-time format in Received and First call |
13 values in 33 rows, 7 used once. 4 date formats and 2 rows with no time | 1, 2 |
| P3 | Job numbers created in one place. The second 26-155 renumbered. Orders Job # picked from a list |
A number used twice. 26136, 137 and two blanks in the Orders tab |
3, 4, 5 |
| P4 | Fixed list for tracker Status, with the date and the invoicing state moved out of it |
15 values in 26 rows. Waits on the decision due 2026-11-25 | 4, 5 |
| P5 | Contact columns in the tracker and the schedule become lookups from the leads sheet | Two phone numbers that disagree | 3 |
| P6 | Email asked on the first call |
17 of 33 rows have one. The report goes out by email | 1 |
Candidates, ranked
| Rank | Candidate | Times per week | Minutes each | Error cost | Build effort | Arithmetic | Score |
|---|---|---|---|---|---|---|---|
| 1 | Inspection report built from a form filled on site | 15 (inspections on the tab, 11/10 to 11/14) | 45 (Priya) | 3 | 3 | 15 × 45 × 3 ÷ 3 | 675 |
| 2 | A lead creates its own row when it arrives, and the office sees who is waiting | 47 (33 rows + 14 with no row) | 6 (Teo) | 3 | 2 | 47 × 6 × 3 ÷ 2 | 423 |
| 3 | Schedule rows fill themselves from the job number | 10.5 (21 rows ÷ 2 full weeks) | 4 (Teo) | 2 | 1 | 10.5 × 4 × 2 ÷ 1 | 84 |
| 4 | Material order drafted from the job, and a warning when a scheduled job has none | 4.5 (18 orders ÷ 4 weeks) | 20 (Marisol) | 2 | 2 | 4.5 × 20 × 2 ÷ 2 | 90 |
| 5 | Invoice list for June when a job is done | 5 (15 jobs done ÷ 3 weeks) | 15 (June) | 2 | 2 | 5 × 15 × 2 ÷ 2 | 75 |
Item 3 is ranked above item 4 with the lower score. The two are within 10% of each other, and the rule gives the place to the one that is cheaper to build.
Why each number
1. Inspection report. Handoffs 4 and 5 in the data map. Priya writes findings on a paper form, the photos stay on her phone, and she builds the report at her desk in the evening. Of 15 inspections, 9 reports went out within a day, 2 took two and three days and 4 had not gone out by Monday. The offer promises 24 hours, so error cost is 3. To build: a form for the phone, a document filled from it, an email draft and a clock. Two tools connected and a document produced, so effort is 3. Needs P1, P2 and P6.
2. A lead creates its own row. Handoffs 1 and 2. A lead sits in one of three inboxes until someone calls, and the row is typed after the call. The middle wait was 235 minutes, 14 leads had no call at all, and 8 of the 33 who were reached had already signed with another roofer. Error cost 3. To build: the web form writes the row with its arrival time at any hour, the sheet lists rows with no first call, oldest first, with a count. A form and a view, so effort is 2. Phone calls and Facebook messages are still typed by a person, but before the call, as the SOP of 2026-11-17 now says. Needs P1 and P2.
3. Schedule rows fill themselves. Handoff 8. Teo retypes customer, address and phone into each schedule row. One phone number is wrong on two rows. A crew that cannot reach the homeowner loses part of a morning, so error cost is 2. To build: Teo types the job number, lookups fill the rest. Effort 1. Needs P3 and P5.
4. Material order drafted from the job. Handoff 7. Marisol orders by phone from memory, and the row is typed afterwards. 2 same-day pickups, one wrong color and one job three working days out with no order. Each is a late start or a second trip, so error cost is 2. To build: when a job gets an install date, a draft order appears with squares, material and color read from the estimate, and a daily check lists scheduled jobs with no order. Marisol still places every order. Effort 2. Needs P3, P4 and the estimate sheet, which was not exported.
5. Invoice list for June. Handoffs 10 and 11. The close reaches June by text. 9 invoices went out 3 to 11 days after the install date, and 5 installed jobs had none yet. Late money is a delay, so error cost is 2. To build: a list of jobs that are Done with a blank Invoiced, each with customer, address and signed amount ready to copy. June still decides the final amount and creates the invoice. Effort 2. The count of 15 jobs is the 14 the tracker marks done plus 26-145, which the schedule marks done. Needs P3 and P4.
Checks on the ranking
- Top item at half the minutes: 15 × 22.5 × 3 ÷ 3 = 337.5. That is below item 2 (423). The top place depends on the 45 minutes being right, and 45 is an estimate. Time five reports before anyone builds.
- Ties: items 3 and 4 are within 10% of each other (84 and 90). The lower build effort goes first.
- Dependencies: P1, P2 and P6 before items 1 and 2. P3 before 3, 4 and 5. P4 waits on Marisol's decision of 2026-11-25.
- Owner's override: none.
Update, 2026-11-25. Priya timed five reports in the week of 2026-11-16: about 45 minutes each (weekly review of 2026-11-23, by Kaizen Brain). The estimate holds, and so does the order. The manual version of item 2 is now running: the Storm lead response SOP has every lead typed on arrival. Item 2 stays on the list for forms that arrive when nobody is in the office.
Stays with a person
| Task | Why a person keeps it | What the system may still do |
|---|---|---|
| Flying the roof, naming each finding, recommending what to do | Judgment. It is the estimator's trade | Hold the form, the photos and the clock |
| Approving a report before it goes out | Judgment, and the company's name is on it | Put the draft in front of the estimator and show how long it has waited |
| The first call to a lead | The customer should hear a person | Show who has waited longest |
| Telling a lead we were slow, or that a report is late | An apology. Marisol or Teo, by phone | Nothing |
| Anything about what insurance will pay | Nobody promises it | Nothing |
| Placing a material order | Money leaves | Draft the order. A person calls it in |
| The final amount when a supplement is pending | Judgment: June and Marisol | Flag the job, show the signed amount |
| Telling a homeowner the crew is delayed | Bad news | Nothing |
Spreadsheet or system
Counted with the signs in Spreadsheet or system.
| Sheet | Liability signs | Which |
|---|---|---|
| Leads sheet | 4 | The same facts are typed elsewhere. Status is drifting into free text. No key. Calls depend on someone noticing an inbox |
| Job tracker | 4 | The same facts are typed elsewhere. Status is free text. A job number is used twice. Orders and invoices depend on someone noticing a status |
| Orders tab, Schedule tab | 1 each | They copy what the tracker holds |
Four signs means each sheet is doing a system's job. Marisol's choice on 2026-11-18: harden both first, because any tool would need the same keys and lists, then build item 1. Count again on 2026-12-16. If the tracker still shows four signs, compare job software against the data map.
Next
- Spec written for: item 1. See Brackenfold · Inspection report spec, written on 2026-11-25 when Marisol asked for it.
- Built: nothing yet.
- Score again: 2026-12-16, or when the other lead tabs and the estimate sheet are exported.